Pumps
|

At Caledonian Mechanical (HVAC/R), we service a lot of walk-in coolers, freezers, and ice machines across the Central Valley. One part that quietly does a ton of work—and causes a ton of headaches when it’s not right—is the liquid line solenoid valve on pump-down systems. This post explains, in plain English, what that valve does, how it ties into defrost and safety, what “passing” means, and why fixing it saves you money and breakdowns.


Quick refresher: pump-down 101

Most low-temp systems (freezers) use pump-down control:

  1. The thermostat or defrost clock turns OFF the liquid line solenoid (de-energizes the coil).
  2. With the valve shut, the compressor keeps running and “pumps” refrigerant out of the evaporator and suction line until the low-pressure switch cuts the compressor off.
  3. Result: the evaporator sits at low pressure (and low refrigerant mass) during the off or defrost period. That prevents liquid migration, floodback, and messy iced-up coils on restart.

When cooling is needed again (or defrost ends), the solenoid is energized (opens), liquid feed returns, suction pressure rises, and the low-pressure switch restarts the compressor.


The liquid line solenoid’s job

  • Normally closed valve on the liquid line feeding the TXV/EEV.
  • Controlled by the space thermostat and/or defrost clock contacts.
  • Opens to allow liquid refrigerant to the coil; closes to let the compressor pump down and stop cleanly.

If this valve doesn’t seal 100% when “closed,” refrigerant leaks—or passes—into the evaporator. That’s where trouble starts.


What does “passing” mean—and why it’s bad

A passing solenoid is leaking through when it should be shut. Symptoms:

  • Compressor won’t stay off after a pump-down; short-cycles on the low-pressure switch.
  • Defrost problems: coil never fully clears because liquid keeps feeding during defrost; excess frost/ice builds back fast.
  • High energy use (kWh): fans, compressor, and crankcase heaters run more than they should; case temp drifts, system hunts.
  • Liquid migration & floodback risk on restart; oil dilution, noisy starts, potential compressor damage.
  • Warm products / temperature swings even though the system seems to “run all the time.”

Real example: A Clovis restaurant we service had a passing liquid solenoid on a walk-in freezer. The valve leaked during defrost, so the system never truly pumped down. Defrosts were ineffective, the compressor short-cycled, and the utility bill climbed. Replacing the valve and cleaning up the circuit brought defrosts back to normal and knocked down runtime and energy use.


Why solenoids pass: mechanical vs electrical

Mechanical causes

  • Debris on the seat (scale, drier desiccant, copper oxide from brazing) prevents a tight seal.
  • Worn seat or plunger, weak return spring, or incorrect valve sizing (oversized valves chatter and wear out).
  • Reversed flow direction or improper install (arrow matters).
  • Moisture/corrosion inside the body; deteriorated seals/O-rings.
  • No pressure differential (some valves need a minimum ΔP to close cleanly).

Electrical/control causes

  • Wrong coil voltage or low voltage at the coil (loose connections, failing transformer, bad contact).
  • Open/shorted coil—gets hot, weak magnet, won’t pull fully closed on de-energize.
  • Defrost clock miswiring—solenoid never fully de-energizes during defrost/off cycle.
  • Stuck relay/contact feeding the coil when it should be off.

How we prove it (no guesswork)

  • Magnet test on the coil: is the plunger moving when commanded?
  • Pressure decay / pump-down test: command the solenoid closed and watch suction pressure. If liquid is sneaking by, suction won’t drop and hold.
  • Temperature touch test on the liquid line downstream of the valve (thermal imaging helps).
  • Electrical checks: measure coil voltage under load, ohm the coil, check control wiring and defrost clock outputs.
  • Cleanliness check: look for drier condition, moisture indicators, and signs of contamination that can foul the seat.

Why repairs pay back quickly

  • Energy: Proper pump-down lets the system rest; compressors don’t short-cycle and fans don’t run pointlessly. That’s lower kWh.
  • Product protection: Defrost works the way it should; you keep coil surfaces clean and box temperature stable.
  • Compressor life: No liquid trickling through during off cycles means less floodback, better oil management, and longer compressor life.
  • Service stability: When controls behave, you get fewer nuisance calls and late-night breakdowns.

What we do when a solenoid is passing

  1. Verify with pressure and electrical tests.
  2. Evaluate contamination: if debris is present, we replace the valve and address the cause—often replace filter-drier(s), pull a deep vacuum, and clean the circuit.
  3. Install the correct valve & coil (proper size, correct voltage), confirm flow direction, and support the line to prevent vibration wear.
  4. Recommission: check superheat/subcooling, verify pump-down cut-out/cut-in, and time a complete defrost cycle to make sure the clock and solenoid are talking to each other.
  5. Document readings and set up preventive maintenance (coil cleaning, door seals, defrost schedule check, drier condition).

How the defrost clock fits in

  • On electric defrost freezers, the defrost clock takes the system out of refrigeration, de-energizes the solenoid, shuts the fans, and powers the heaters.
  • With the solenoid closed, the compressor pumps down and stops on low pressure while heaters clear the coil.
  • At defrost termination (by time/temperature/pressure), the clock re-energizes the solenoid, the low-pressure switch restarts the compressor, and fans resume after a short delay so you don’t blow water off the coil.
  • If the solenoid passes during defrost, you get warm/cold fighting each other—inefficient defrosts, refreeze on the coil, long runtimes, and poor case temps.

Owner tips to stay out of trouble

  • Watch door habits: long propped-open doors force longer run and defrost times.
  • Mind the driers: if we note recurring moisture/debris, let us change drier cores before valves and TXVs start sticking.
  • Keep schedules current: defrost frequency and duration should match your load and traffic—too little or too much both hurt you.
  • Plan PMs: a small quarterly check (amp draws, superheat, pump-down verification, coil/fan health) beats emergency visits.

If your walk-in is short-cycling, struggling to defrost, or just “never quite gets there,” the liquid line solenoid is high on the suspect list. We’re happy to test it and show you the readings so you can see the problem (and the savings) in black and white.

Caledonian Mechanical — HVAC/R Services
Walk-ins • Reach-ins • Ice machines • Controls • PM programs
(559) 753-1775 • caledonianhvac.com

Pro tip: If you’re seeing rising kWh and more frost than usual, don’t wait. A passing solenoid can quietly drive up your utility bill for months before it fails outright.